OPWC Projects

OPWC 32C - Kolbe Road 

Week of 08/12/2019

South Kolbe Milling

005

North Kolbe Milling

001

Kolbe pavement repairs

010

Kolbe paving intermediate

004

Kolbe paving surface asphalt

008

OPWC 33A  - Currently Under Construction

Week of 9/30/2019

Rita Drive Removal and Replacement

025

Week of 9/23/2019

Drainage improvements.

258

Week of 9/16/2019

Casting Adjustments and Underdrain.

241

Week of 9/9/2019

Concrete prep work and paving. Field issues, storm and void under existing pavement.

288

Week of 9/2/2019

Concrete Prep work and paving.

178

Week of 8/26/2019

Concrete Paving and Asphalt Paving.

004

Week of 08/19/2019

Base repairs. Concrete removal for new concrete placement. New curb and gutter placement. Steel placement for 

001

Week of 08/12/2019

Base, water valve, and storm repairs. New concrete work.

016

Week of 07/29/2019

Concrete Work and Curb Ramp Removals and Replacements - Asphalt Roadways

077

Week of 07/22/2019

Milling of Asphalt Roadways

006

OPWC 33B - Under Construction

Week of 11/04/2019

Curb and Gutter Removal on Fiesta

Week of 10/21/2019

Lemonwood Cul-De-Sac Pour

Week of 10/7/2019

Concrete removal and underdrain.

Lemonwood removal of NB lane

Week of 9/30/2019

Asphalt and Concrete Paving.

Lemonwood Pave 2

Week of 9/23/2019

Asphalt paving. Sidewalks. Curb and Gutter Installation.

Belmont Sidewalks

Week of 9/16/2019

Asphalt base repair

Belmont Base Repair II

Week of 9/9/2019

Asphalt milling various streets.

Belmont Milling