PID 101446 - Resurfacing-Urban Paving City of Lorain

LOR 58 24.66 (Amherst/Lorain Corp (JNT Line N. of Cooper Foster Rd.) to 27.56 (US6)

Project Information:

Contractor: To Be Determined

Project Manager: Luke Wysocki

Cost: Local cost share: $490,000.00 for construction and $35,000.00 for construction inspection 

Proposed Construction Start, date:06/01/2021

Scope: The intent of this project is to mill and fill the existing roadway completely within City of Lorain limits. Bridge work will be completed as required. Curb ramps will be upgraded to current ADA standards.